Asset Relocation Works
TfNSW Lisarow
Level 1 ASP Projects
Client
CMC
Value
$2.15 million
Scope
Overhead 66kV works and underground 11kV & Auxiliary works with supplementary streetlighting
Project Highlights
- All maintenance and risk assessment of plant and equipment was conducted onsite by Syscon, avoiding downtime.
- Removal of groundwater by installing spear points so team could continue trenching process and placing conduits in the ground.
- Strategic coordination of nightworks to accommodate additional outages minimising disruption to local business and residents.
![CMC Ourimbah-Lisarow electrical asset relocation Overhead underground electrical works with & Auxiliary works plus supplementary streetlighting in Lisarow-Ourimbah, NSW](https://syscon.net.au/wp-content/uploads/CMC-Ourimbah-Lisarow-electrical-asset-relocation.jpg)